The Temane Combined Cycle Thermal Power Plant, in the province of Inhambane,
will generate 450 MW of electricity that will be injected into the national grid to meet the country’s needs and to supply clean and low-cost energy for the regional development of the Southern African Development Community (SADC).

The forecasted generation of the electricity results from the USD 760 million investment for the Temane Natural Gas Project, particularly the development of the additional natural gas reservoirs that are around the Inhassoro and Temane fields, in Inhassoro district, Inhambane province, under the oil sharing contract that had the development plan revised by the Government in September 2020.

It should be noted that the Final Investment Decision under the Oil Sharing Contract was taken on Friday, February
It will also allow the production of 23 million Giga joules of natural gas per year, which will be used for the production of 30 thousand tons of cooking gas per year in what will be the first unit of its kind in the country.

In a press release to which “Noticias” had access yesterday, the Ministry of
Mineral Resources and Energy (MIREME) emphasizes that the production of 30 thousand tons per year of cooking gas (LPG), will make Mozambique stop importing about 75% of the volume currently 75% of the volume currently purchased from abroad.

The project also includes the production of 4,000 barrels of light oil per day for
export.
According to MIREME, the local production of LPG will boost the massification of the
use of cooking gas, contributing to the reduction of deforestation.

According to the source, the construction of the natural gas production infrastructures should begin in July of this year and will directly employ more than 3,000 Mozambicans and generate thousands more indirect jobs in the next three years.

“The Final Investment Decision taken by Sasol will enable the materialization of the commitment made by the of the commitment made by the President of the Republic, Filipe Nyui, when he took office in January 2020, on the need for the internal transformation of Mozambique’s natural gas, with a view to accelerating the industrialization and economic development of the development of the country”, highlights the source

SUBSCRIBE TO GET OUR NEWSLETTERS:

See Also

SUBSCRIBE TO GET OUR NEWSLETTERS:

Scroll To Top

We have detected that you are using AdBlock Plus or other adblocking software which is causing you to not be able to view 360 Mozambique in its entirety.

Please add www.360mozambique.com to your adblocker’s whitelist or disable it by refreshing afterwards so you can view the site.